Deployment Plan¶
Target: Functional mesh network covering Justin, TX by end of summer 2026.
Timeline Overview¶
| Phase | Duration | Target Completion |
|---|---|---|
| Planning & Approvals | 6 weeks | Mid-March |
| Hardware Acquisition | 6 weeks | End of March |
| Infrastructure Deployment | 10 weeks | Mid-June |
| User Onboarding | 12 weeks | End of July |
| Testing & Optimization | 6 weeks | End of July |
| Web Integration | Ongoing | End of July |
Buffer: 4-6 weeks before end of summer for contingencies.
Phase 1: Planning & Approvals¶
February - Mid-March 2026
- [x] Complete site survey for 5-10 repeater locations
- [x] Submit water tower installation request
- [ ] Submit secondary site requests (2-3 locations)
- [ ] Secure first 3 site approvals
- [ ] Initiate CERT/emergency management outreach
- [ ] Finalize infrastructure node placement map
Approvals Timeline
Approvals may extend beyond this phase. Deployment can begin as approvals come through.
Phase 2: Hardware Acquisition¶
February - End of March 2026
- [x] Procure 3-5 additional infrastructure nodes (Meshtastic)
- [ ] Procure 2-3 MeshCore repeater nodes (1 of 2-3 acquired)
- [x] Acquire solar panels and batteries for remote sites
- [ ] Acquire weatherproof enclosures
- [ ] Procure MQTT gateway hardware (1-2 units)
- [ ] Build inventory of user nodes for distribution/sale
Parallel Phase
Runs parallel with Phase 1. Order early to account for shipping delays.
Phase 3: Infrastructure Deployment¶
March - Mid-June 2026
- [ ] Deploy water tower repeater (pending approval)
- [ ] Deploy secondary site repeaters (2-3 sites)
- [ ] Install solar power systems at remote sites
- [ ] Deploy MQTT gateway nodes (1-2 locations)
- [ ] Verify repeater-to-repeater connectivity
- [ ] Establish NTXMesh overlap coverage
Staggered Deployment
Begin as soon as first approval + hardware arrives. Stagger deployments to validate each site.
Phase 4: User Onboarding¶
April - End of July 2026
- [ ] Publish user node configuration guides
- [ ] Create "Getting Started" onboarding page
- [ ] Recruit 10 initial users
- [ ] Recruit 20 additional users (total: 30)
- [ ] Establish node distribution/sales process
- [ ] Host community demo/training session
User Targets
Start recruiting once 2-3 repeaters are live. Target 10 users by May, 30 by end of July.
Phase 5: Testing & Optimization¶
May - End of July 2026
- [ ] Verify coverage across Justin city limits
- [ ] Test rural area coverage
- [ ] Optimize channel settings based on traffic
- [ ] Document dead zones and plan remediation
- [ ] Stress test with increased traffic
- [ ] Validate emergency message routing
Iterative Process
Begins once infrastructure is 50%+ deployed. Continuous refinement based on real-world usage.
Phase 6: Web Integration¶
Ongoing - End of July 2026
- [ ] Status dashboard showing live node count
- [ ] Mesh map displaying coverage
- [ ] Documentation for all deployed nodes
- [ ] Public status page for network health
Existing Foundation
Core functionality already exists. Enhancements as network grows.
Future: MeshCore Expansion¶
Q4 2026+
- Parallel deployment may begin once Meshtastic infrastructure stable
- Separate planning document when ready
- Will leverage same physical sites where possible
Progress Updates¶
Last updated: February 2026
Update this page as tasks complete. Adjust percentages to reflect actual progress.